Calculate concrete volume, bags needed, and rebar estimation for slab projects. Includes waste percentage and ready-mix truck recommendations.
Calculate concrete volume, bags needed, and rebar estimation for slab projects
Thickness Guidelines
Formula
Volume (cu yd) = (Length × Width × Thickness) / 27Where all dimensions are converted to feet. One cubic yard equals 27 cubic feet. Includes waste percentage for spillage and uneven ground.
| Slab Size | Thickness | Cubic Yards | 60 lb Bags | 80 lb Bags |
|---|---|---|---|---|
| 8' × 10' | 4" | 0.99 | 66 | 50 |
| 10' × 10' | 4" | 1.23 | 82 | 62 |
| 10' × 12' | 4" | 1.48 | 99 | 74 |
| 12' × 12' | 4" | 1.78 | 119 | 89 |
| 12' × 16' | 4" | 2.37 | 158 | 119 |
| 16' × 16' | 4" | 3.16 | 211 | 158 |
| 16' × 20' | 4" | 3.95 | 264 | 198 |
| 20' × 20' | 4" | 4.94 | 330 | 247 |
| 20' × 24' | 4" | 5.93 | 395 | 297 |
| 24' × 24' | 4" | 7.11 | 475 | 356 |
Where all dimensions are in feet. One cubic yard equals 27 cubic feet.
Rebar (reinforcing bar) strengthens concrete and prevents cracking. It's laid in a grid pattern with pieces running both lengthwise and widthwise. Standard #4 rebar (1/2" diameter) is commonly used for residential slabs. The rebar should be positioned in the lower third of the slab thickness.
For large projects (over 2-3 cubic yards), ready-mix concrete delivery is more economical and ensures consistent quality throughout the pour.
Sidewalks, patios, garage floors, light foot traffic
Driveways for passenger vehicles
Heavy-duty driveways, RV parking, industrial floors
Foundations, structural slabs, heavy equipment areas
Multiply length × width × thickness (all in feet) to get cubic feet, then divide by 27 to convert to cubic yards. For example, a 10' × 12' × 4" slab = 10 × 12 × 0.333 = 40 cubic feet = 1.48 cubic yards.
Thickness depends on the application: 4" for sidewalks and patios, 4-6" for driveways and garage floors, 6" for heavy-duty applications, and 8"+ for foundations. Always check local building codes.
Add 10% for waste to account for spillage, uneven ground, and form variations. For complex shapes or uneven terrain, consider adding 15-20%.
Bagged concrete is economical for small projects under 1 cubic yard. For projects over 2-3 cubic yards, ready-mix delivery is more cost-effective and ensures consistent quality.
Standard rebar spacing is 16" on center for most residential slabs. Use 12" spacing for heavy-duty applications like driveways with heavy vehicles. Light-duty patios may use 18-24" spacing or wire mesh instead.
A 60 lb bag covers about 0.45 cubic feet, and an 80 lb bag covers about 0.60 cubic feet. For a 1 cubic yard project (27 cu ft), you'd need about 60 bags of 60 lb mix or 45 bags of 80 lb mix.